Turnkey Industrial Plant Setup Support
From initial connected load calculations and 11kV/33kV substation erection to main power control centers, overhead busducts, utility air piping, machine cabling, and statutory CEIG approvals—delivering operational factories on schedule.
New Plant Setup Desk
Connect with our senior turnkey project engineers for site layout and load schedule review.
End-to-End Infrastructure for New & Expanding Plants
We bridge the gap between civil factory buildings and live machine production, executing all electrical, utility, earthing, and statutory milestones under single-point accountability.
HT Substation & Power Ingress
Connected load calculations, utility DISCOM power sanction liaison, 11kV/33kV indoor and outdoor substation erection, power transformers, and HT metering kiosk setups.
- Connected load scheduling & diversity optimization
- Transformer plinth installation & oil BDV testing
- HT vacuum circuit breaker (VCB) synchronization
Main LT Switchboards & Busducts
Main Power Control Center (PCC) erection, DG synchronization AMF panels, APFC capacitor banks for power factor maintenance, and overhead sandwich busbar trunking systems.
- Main switchboard erection up to 6300A
- Aluminium & copper sandwich busway installation
- Auto-mains failure (AMF) dual power changeovers
Machine Drops & Bay Distribution
Overhead heavy-duty GI cable ladder trays, machine-level sub-distribution boards (SDB), localized rotary isolators, and final power terminations to production machinery.
- Dedicated machine drops with individual isolators
- Armoured power & shielded control cable laying
- Numbered ferrule tagging & loop continuity testing
Plant Compressed Air & Utility Piping
Layout and erection of the central utility room: rotary screw air compressors, refrigerated air dryers, zero-loss condensate drains, and overhead aluminum pneumatic ring mains.
- Aluminum modular compressed air piping networks
- Process cooling water supply & return manifolds
- Pneumatic pressure drop testing & leak validation
Earthing Grids & Industrial Illumination
Chemical maintenance-free earthing rings (< 1.0 Ohm), ESE lightning arresters, plant-wide high-bay LED illumination, emergency exit lighting, and perimeter floodlights.
- Substation & electronic clean earthing grids
- Lux calculations compliant with factory floor norms
- Automatic lighting distribution boards with timer relays
Statutory CEIG Approvals & Energization
Complete regulatory clearance package: CAD drawing submission, relay test certificates, earth pit logs, inspectorate site escorting, and pre-commissioning safety approvals.
- As-Built Single Line Diagram (SLD) CAD sign-off
- CEIG site inspection coordination & punch-list closure
- Official power energization permission certificate
Plant Setup Scope & Quality Benchmarks
Stringent standards applied across every engineering phase of the new facility setup.
| Plant Setup Package | Technical Engineering Scope | Governing Codes & Standards | Testing & Commissioning Protocol | Key Deliverable |
|---|---|---|---|---|
| HT Ingress & Substation | 11kV / 33kV Substation, Transformers up to 5MVA | IS 2026 / CEA Regs 2010 | Oil BDV test, Ratio & Winding resistance, VCB timing | CEIG Approval Certificate |
| Main LT Switchboards | 415V PCC, MCC, AMF DG Boards, APFC Banks | IEC 61439-1 / IS 8623 | Busbar torque audit, 1000V Megger test, Shunt trip tests | Calibrated Relay Certificates |
| Overhead Busduct & Trays | Sandwich Busways up to 4000A, HDG Ladder Trays | IEC 61439-6 / IS 2062 | Phase insulation test, 86-micron HDG galvanizing check | Busbar Alignment & Route Map |
| Machine Feeder Cabling | XLPE Armoured Copper/Aluminium Cables, SDBs | IS 7098 / IS 1255 | Insulation resistance (Megger), phase sequence check | Cable Schedule & Ferrule Chart |
| Pneumatic Utilities | Air Compressors, Dryers, Aluminum Ring Main | ISO 8573 Compressed Air | 24-hr pressure hold test, dew point hygrometer log | Pneumatic Schematic & Leak Log |
| Earthing & Lightning | Chemical Pipe Earth Pits, Copper Strips, ESE Mast | IS 3043-2018 / IEEE 80 | Fall-of-potential test < 1.0 Ohm, strike radius test | Numbered Earth Pit Test Logs |
Our 5-Stage Plant Setup Roadmap
A proven turnkey lifecycle delivering on-schedule factory startups with zero safety incidents.
Load Sizing & Layout Review
Connected load calculations, machinery power demand matrices, civil layout evaluation, and DISCOM power sanction planning.
Detailed Engineering & SLD
CAD Single Line Diagram (SLD) creation, cable sizing schedules, panel layout drafting, and submission to statutory CEIG authorities.
Substation & Heavy Power
Erection of 11kV/33kV substations, power transformers, main PCC switchboards, earthing grids, and overhead sandwich busducts.
Machine Drops & Utilities
Installation of machine sub-distribution boards, localized isolators, production bay lighting, and compressed air utility ring mains.
Testing, CEIG & Power On
Pre-commissioning Megger/Hi-Pot tests, CEIG inspectorate walk-through escorting, and official plant-wide power energization.
Frequently Asked Questions
Answers to common questions regarding greenfield and brownfield plant electrification.
Planning a New Factory Setup or Plant Expansion?
Share your architectural layout, equipment machinery list, or Single Line Diagram (SLD). Our senior industrial project engineers will prepare a turnkey infrastructure proposal with milestone timelines.